一项政府批准的税收变更必须在六个月内实施。项目经理应该做什么?
2244 次浏览
- A、Inform all relevant stakeholders of the change and the identified response. 将该变更与确定的应对措施通知给所有相关相关方。
- B、Include the change in the project cost estimate,and inform all relevant stakeholders. 将该变更包含在项目成本估算中,并通知所有相关相关方。
- C、Meet with all relevant stakeholders to discuss its impact. 与所有相关相关方开会,讨论其影响。
- D、Meet with appropriate departments to communicate the agreed upon project response to all stakeholders. 与相关部门开会,向所有相关方传达商定的项目应对措施。
微信公众号