根据一位高级成员的意见,实施纠正措施以解决设计问题,实施后,该团队发现纠正措施未能提高设计质量。若要避免这个问题,项目经理应该事先做什么?
2382 次浏览
- A、Referred to the change management plan,and ensure that change requests were formally authorize 参考变更管理计划,并确保变更请求得到正式授权。
- B、Ensured the design's corrective action was inspected and held a lesson learn session. 确保检查设计的纠正措施并召开经验教训会议。
- C、Identified the risks,and documented the sources of overall project risks. 识别风险,并记录整体项目风险的来源。
- D、Consulted the quality management plan,and assured that inspections and audits were conducted 查阅质量管理计划,并确保进行检查和审计。