A、Recognize that there is a change in stakeholders structure and tailor communications to this group 认识到相关方结构发生了变化,并量身定做与这个团队的沟通
B、Continue to work according to the initial plan while recognizing that the project now includes additional stakeholders. 按照最初的计划继续工作,同时认识到该项目现在包括其他相关方
C、Organize a meeting for the team with the new steering committee and continue to work on the project 为团队组织一次与新的指导委员会一起召开的会议,继续进行项目工作
D、Share the current status report with the new committee 与新的委员会分享当前的状态报告