一个项目延迟交付,且需要进行变更才能获得理想的可交付成果质量级别。项目经理签发正式的变更请求,并与所有相关方沟通变更。然后项目经理得知这种沟通方式未能满足相关方的期限。项目经理应该怎么做?
用户挑战记录
选择了: Review the communications management and stakeholder management plans. 审查沟通管理计划和相关方参与计划。
登录后查看详情
选择了: Follow the communications management plan, and issue a status report. 遵循沟通管理计划,并签发一份状态报告。
登录后查看详情
选择了: Review the communications management and stakeholder management plans. 审查沟通管理计划和相关方参与计划。
登录后查看详情
选择了: Review the communications management and stakeholder management plans. 审查沟通管理计划和相关方参与计划。
登录后查看详情
选择了: Review the communications management and stakeholder management plans. 审查沟通管理计划和相关方参与计划。
登录后查看详情
选择了: Review the communications management and stakeholder management plans. 审查沟通管理计划和相关方参与计划。
登录后查看详情
选择了: Review the communications management and stakeholder management plans. 审查沟通管理计划和相关方参与计划。
登录后查看详情
选择了: Issue a change request to include stakeholders’ expectations in the project management plan. 签发变更请求,在项目管理计划中包含相关方的期限。
登录后查看详情
选择了: Follow the communications management plan, and issue a status report. 遵循沟通管理计划,并签发一份状态报告。
登录后查看详情
选择了: Meet with the project sponsor to better understand stakeholders’ expectations. 与项目发起人开会,以更好地了解相关方的期限。
登录后查看详情
相关题目
- 一家公司的管理团队希望雇佣一名资源,来管理对公司现有产品的软件升级。该产品是某个部门多个产品的其中一个产品,且该部门还有其它重要活动。那么应该选择下列哪一个候选人来管理软件更新?
- 在项目收尾期间,发现一个问题,但在这个阶段,该项目的资源已经解散。在解散资源之前,项目经理应该事先做什么?
- 在项目过程中,发生了一个意外。该事件影响了项目成本,但是未影响到时间。该事件之前被项目团队识别为一项潜在风险。若要限制该事件对于项目成本的影响,项目经理应该怎么做?
- 您被要求生产一个10米长的管,并且您正在生产12.1米,11.98米,12.12米,12.08等范围内的管。这意味着:
- 在规划中,项目团队识别到一个质量不合格风险,并为这个风险准备了一份行动计划。若要避免项目执行过程中的不合格,项目经理应进行下列哪一项?
推荐
想要系统学习?查看我们的 模拟试卷