项目团队正在研究一个项目的新批准范围,监管团队在提供对该变更必要的意见方面是不可或缺的。但是,该团队发现监管部门未被列为项目相关方。项目经理下一步应该怎么做?
用户挑战记录
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Instruct the project team to verify the need for this change. 指示项目团队确认是否需要进行这项变更
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Create a new change request and ensure that the regulatory team is involved in the process. 创建一项新的变更请求并确保监管团队参与这个过程
登录后查看详情
选择了: Ensure that the regulatory team is included in the change control board (CCB). 确保监管团队包含在变更控制委员会 (CCB)中
登录后查看详情
相关题目
- 一家公司的管理团队希望雇佣一名资源,来管理对公司现有产品的软件升级。该产品是某个部门多个产品的其中一个产品,且该部门还有其它重要活动。那么应该选择下列哪一个候选人来管理软件更新?
- 在项目收尾期间,发现一个问题,但在这个阶段,该项目的资源已经解散。在解散资源之前,项目经理应该事先做什么?
- 在项目过程中,发生了一个意外。该事件影响了项目成本,但是未影响到时间。该事件之前被项目团队识别为一项潜在风险。若要限制该事件对于项目成本的影响,项目经理应该怎么做?
- 您被要求生产一个10米长的管,并且您正在生产12.1米,11.98米,12.12米,12.08等范围内的管。这意味着:
- 在规划中,项目团队识别到一个质量不合格风险,并为这个风险准备了一份行动计划。若要避免项目执行过程中的不合格,项目经理应进行下列哪一项?
推荐
想要系统学习?查看我们的 模拟试卷