A、Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
B、Notify project stakeholders that any estimates submitted by the SME must be increased by 20% percent. 通知项目相关方,该主题专家提交的任何估算必须增加20%.
C、Ignore previous issues with estimates from this SME and continue with the process unchanged. 忽略与该主题专家有关的估算问题,并继续保持该过程不变.
D、Remove the SME from the project and request a resource who can provide more accurate estimates. 将该主题专家从项目中排除并请求可提供更准确估算的资源.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.
Periodically review objectives and requirements with the SME during estimation and use other resources to review the submitted estimates. 在估算期间与该主题专家定期审查目标和需求,并使用其他资源审查提交的估算.