一个在国外工作的项目团队被转移到项目经理所在的国家。下一个工作周是这个团队的宗教节目,这些团队成员要求在这一周放假。项目经理应该怎么做?
2049 次浏览
- A、Check with the legal department regarding this team’s contract conditions and adhere to their responses and suggestions 与法律部门核对该团队的合同条件,并遵守其答复与建议
- B、Grant the request and allow the original team off as a reward for their hard work 批准该请求,并让原来的团队休假,作为他们辛勤工作的奖励
- C、Grant the request as an acknowledgement of its importance. 批准该请求,作为对其重要性的认可
- D、eny the request to avoid a negative impact on the schedule 拒绝该请求,以避免对进度计划造成负面影响解析
微信公众号