项目合同规定了专业资源。在审查项目范围时,项目经理和承包商确定采购小组应选择工料合同(T&M),而不是固定总价(FFP)合同。项目经理应该怎么做?

中级单选题3281 次浏览0 人挑战

用户挑战记录

mshare
mshare挑战成功

选择了: Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同

登录后查看详情

mshare
mshare挑战失败

选择了: Inform the contractor that the contract cannot be changed since it is a binding and legal document. 通知承包商合同不能变更,因为合同是具有约束力的法律文件

登录后查看详情

fengshu1117
fengshu1117挑战成功

选择了: Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同

登录后查看详情

fengshu1117
fengshu1117挑战失败

选择了: Perform a variance analysis as part of the ontrol osts process 执行偏差分析,作为控制成本过程的组成部分

登录后查看详情

Louiszhou
Louiszhou挑战成功

选择了: Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同

登录后查看详情

channelyhx
channelyhx挑战成功

选择了: Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同

登录后查看详情

channelyhx
channelyhx挑战失败

选择了: Wait for the procurement group to initiate a contract change 等待采购小组提出合同变更

登录后查看详情

t1t2tx
t1t2tx挑战成功

选择了: Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同

登录后查看详情

t1t2tx
t1t2tx挑战失败

选择了: Perform a variance analysis as part of the ontrol osts process 执行偏差分析,作为控制成本过程的组成部分

登录后查看详情

Angus
Angus挑战成功

选择了: Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同

登录后查看详情