项目合同规定了专业资源。在审查项目范围时,项目经理和承包商确定采购小组应选择工料合同(T&M),而不是固定总价(FFP)合同。项目经理应该怎么做?
2987 次浏览
- A、Inform the contractor that the contract cannot be changed since it is a binding and legal document. 通知承包商合同不能变更,因为合同是具有约束力的法律文件
- B、Seek approval of a change request to amend the contract 寻求批准变更请求,修改合同
- C、Perform a variance analysis as part of the ontrol osts process 执行偏差分析,作为控制成本过程的组成部分
- D、Wait for the procurement group to initiate a contract change 等待采购小组提出合同变更