—个项目已经发生偏差几个月了,这种状态通过电子邮件在每周报告中发送给所有相关方。一位关键相关方刚刚得知这一偏差并对只通过电子邮件通知感到不安,若要预防这个问题,项目经理应该事先做什么?
2532 次浏览
- A、Verified that all stakeholders and received and understood each status report 确认所有相关方都收到并理解每份状态报告
- B、Chosen the appropriate communication method for each stakeholders 为每一个相关方选择适当的沟通方法
- C、Engaged directly with key stakeholders about critical issues or project deviations 直接与关键相关方就重要问题或项目偏差进行接洽
- D、Planned periodic meetings with key stake stakeholders to report project status 计划与关键相关方定期举行会议以报告项目状态
微信公众号