—个项目已经发生偏差几个月了,这种状态通过电子邮件在每周报告中发送给所有相关方。一位关键相关方刚刚得知这一偏差并对只通过电子邮件通知感到不安,若要预防这个问题,项目经理应该事先做什么?
用户挑战记录
选择了: Chosen the appropriate communication method for each stakeholders 为每一个相关方选择适当的沟通方法
登录后查看详情
选择了: Chosen the appropriate communication method for each stakeholders 为每一个相关方选择适当的沟通方法
登录后查看详情
选择了: Verified that all stakeholders and received and understood each status report 确认所有相关方都收到并理解每份状态报告
登录后查看详情
选择了: Chosen the appropriate communication method for each stakeholders 为每一个相关方选择适当的沟通方法
登录后查看详情
选择了: Chosen the appropriate communication method for each stakeholders 为每一个相关方选择适当的沟通方法
登录后查看详情
选择了: Engaged directly with key stakeholders about critical issues or project deviations 直接与关键相关方就重要问题或项目偏差进行接洽
登录后查看详情
选择了: Verified that all stakeholders and received and understood each status report 确认所有相关方都收到并理解每份状态报告
登录后查看详情
选择了: Planned periodic meetings with key stake stakeholders to report project status 计划与关键相关方定期举行会议以报告项目状态
登录后查看详情
选择了: Chosen the appropriate communication method for each stakeholders 为每一个相关方选择适当的沟通方法
登录后查看详情
选择了: Engaged directly with key stakeholders about critical issues or project deviations 直接与关键相关方就重要问题或项目偏差进行接洽
登录后查看详情
相关题目
- 一家公司的管理团队希望雇佣一名资源,来管理对公司现有产品的软件升级。该产品是某个部门多个产品的其中一个产品,且该部门还有其它重要活动。那么应该选择下列哪一个候选人来管理软件更新?
- 在项目收尾期间,发现一个问题,但在这个阶段,该项目的资源已经解散。在解散资源之前,项目经理应该事先做什么?
- 在项目过程中,发生了一个意外。该事件影响了项目成本,但是未影响到时间。该事件之前被项目团队识别为一项潜在风险。若要限制该事件对于项目成本的影响,项目经理应该怎么做?
- 您被要求生产一个10米长的管,并且您正在生产12.1米,11.98米,12.12米,12.08等范围内的管。这意味着:
- 在规划中,项目团队识别到一个质量不合格风险,并为这个风险准备了一份行动计划。若要避免项目执行过程中的不合格,项目经理应进行下列哪一项?
推荐
想要系统学习?查看我们的 模拟试卷