在执行一个潜艇现代化项目期间,客户要求安装新的潜望镜。项目经理必须怎么做?
3172 次浏览
- A、Check the feasibility, prepare the budget, and obtain change request approval 检查可行性,准备预算,并获得变更请求批准
- B、Conduct the Perform Integrated Change Control process, obtain budget approval and execute the change, request. 执行实施整体变更控制过程,获得预算批准,并执行变更请求
- C、Prepare a change request obtain approval from the change control board (B), and implement the change. 准备变更请求,获得变更控制委员会(B)的批准,并实施变更
- D、Check the feasibility, prepare a quote and the budget, and obtain customer approval. 检查可行性,准备报价和预算,并获得客户的批准