在项目实施期间,项目发起人要求项目经理审查和减轻新报告的风险。审查期间,项目经理确定只有一个是风险,而其它的都是问题。下列哪一项会被认为是风险?
2562 次浏览
- A、New market regulations will soon be approved, which may require a revising the project scope 新的市场法规很快的获得批准,这可能需要修订项目范围
- B、A design defects in identified in the initial project stage 在项目初始阶段识别到设计缺陷
- C、A subject matter expert (SME) leaves the project to joins a competitors company 一名主题专家(SME)离开项目,加入竞争对手的公司
- D、The contingency reserve has been depleted by approved change requests 应急储备已被批准的变更请求耗尽