The Estimate Activity Resource process is closely coordinated with the (73)process.

1068 次浏览
  • A、Estimate Costs
  • B、Sequence Activities
  • C、Plan Communications
  • D、Conduct Procurements
估算活动资源与成本估算是密切联系的